The tension: Two decades of documented flood harm against a final piece of infrastructure whose opening has slipped from 2026 to 2027.

Lisgar, in Ward 10, has two decades of documented flood harm. Four automated pumping stations are planned. As of June 30, 2026 two were operating, and a third was expected to be fully operational that July.

The fourth station's opening has slipped from 2026 to 2027, despite residents asking for it to be fast-tracked, including a formal letter asking the Mayor to use her strong-mayor powers.

If a project is late because of how the work is sequenced and procured, rather than because it is unfunded, that is something council controls. It is also something a candidate can be asked to commit to.

The questions below ask who answers for a missed date, and to whom.

Resolution Options

Ways this tension could be resolved. Each question below tests one of them.

Questions you can ask

To: ward-10City staff told council in September 2025 that the pumping-station delay was not a funding issue, and the City has said council approved $5.6 million for the fourth station. Will you commit to a firm, published completion date for the fourth Lisgar pumping station, and to personally escalating any further delay to the Mayor's office in writing?

Tests: Fix a published date and escalate any slip

Heard an answer to this?

To: ward-10The fourth pumping station's opening has slipped from 2026 to 2027, and its construction start from 2025 into 2026, despite residents writing to the Mayor directly. Will you commit to a rule that any City project missing its published completion date must come back to council with a written explanation before a new date is set?

Tests: Make a missed date come back to council

Heard an answer to this?

Candidates on record

3 candidates are on record on this issue. Every candidate in this race is searched the same way. Only candidates who have said something in public on this issue are named here, with a link to the source; the others are counted by race below. The full record for every candidate is on Candidates.

Ward 10

  • Aatish Jamal (campaign site) · Instagram
    • reported on record: In an October 8, 2026 post on his campaign site, Jamal says the 2021 schedule for the remaining Lisgar pumping stations was a preliminary estimate rather than a fixed commitment. He would work with staff toward the earliest technically achievable completion and publish a tracker of each project's status, budget, next milestone and expected completion, and says: "Where dates change, the explanation should identify what caused the change". He does not commit to a firm completion date for the fourth station, to escalating delays to the Mayor's office, or to a rule that a project missing its published date comes back to council. [source]
  • Hamza Bajwa (campaign site) · Instagram
    • reported on record: Bajwa's platform commits him to "Press for a public, time-bound flood-mitigation plan with clear construction milestones", to demand an explanation for the pumping-station delays, and to "Require regular public progress reports so Lisgar residents can see what has been funded, built, and delayed." A position for a published schedule and public reporting on the Lisgar works. It does not name a completion date for the fourth pumping station, commit to escalating a delay to the Mayor's office in writing, or propose a rule for projects that miss their published date. [source]
  • Sue McFadden (campaign site) · Facebook · X · Instagram
    • reported on record: McFadden's re-election site says "Lisgar's third of four pumping stations is now operational as of summer, 2026" and that, like the first two "further north along the Sixteen Mile Creek", it "is designed to remove water from the trunk of the Foundation Drain Collector sewer system, reducing surcharging that causes basement flooding during large rainstorm events." A statement of the works' progress, made as the sitting Ward 10 councillor. It does not give an opening date for the fourth station, commit to escalating a delay to the Mayor's office in writing, or propose a rule for projects that miss their published date. [source]

2 other candidates searched 2026-10-09: no public position found yet. Every candidate in this race →

The full story

The record behind the questions, with a source at each claim.

Flooding in Lisgar dates to 2008. In the summer of 2024 two storms described as “once-in-a-century” (106mm of rain on July 16, and up to 170mm across parts of Mississauga and the GTA on August 17 and 18) left Lisgar among the areas severely impacted; in Ward 10 as a whole, about 500 homes were flooded. Residents cite roughly $125 million in cumulative losses — a residents’-association figure, not an independently audited City number, and we cite it as such.

As of June 30, 2026, two of the four planned automated pumping stations were operating: the first at Cactus Gate since 2021, the second at Smoke Tree since 2025, both north along Sixteen Mile Creek. A third, immediately south of Doug Leavens Boulevard, was expected to be fully operational in July 2026 — at that date its control panel had been tested and the remaining equipment was still being tested. The fourth — requested to be fast-tracked to 2026 — was, as INsauga reported on June 30, 2026 citing an earlier City statement, on track to open in 2027, despite direct resident appeals including a formal letter to the Mayor, council and senior City staff asking her to use her strong-mayor powers.

Where the fourth actually stands. Ward 10 Councillor Sue McFadden told residents on June 30, 2026 that its detailed design is complete and construction was scheduled to begin later that summer, at the east edge of Osprey Marsh just south of Osprey Boulevard. That is the most specific public answer we have found, searching as of 2026-10-02, to the question this page puts to candidates — and it is a councillor’s newsletter reported by one outlet, not a City report, so read it as a status update rather than a commitment.

Corrected 2026-08-09. This page previously said “three of four planned automated pumping stations are built.” Its own fact-check entry never said that — the ledger had recorded “Two of four planned pumping stations were operational by 2025, a third expected mid-2026” since July 29. The page and the ledger disagreed for eleven days and the ledger was the correct half. Nothing sourced the completion claim; it asserted a finished state that no source established. See corrections — a fix in one twin is not a fix.

The money is not the obstacle. At the September 2025 council meeting where residents asked for the fourth station to be fast-tracked, City director Emma Calvert said the delay was not a funding issue — budgets had been allocated annually — and explained that the four stations proceed individually through design, tender and construction, which is what sets the schedule. The Pointer reported that the City had attributed the 2027 date to “procurement delays”, and the City’s September 12, 2025 statement said a pre-qualification for the fourth station was then in-market. On September 12, 2025, in a statement to The Pointer, the City said council had approved $5.6 million for the fourth station’s design and construction, with construction expected to start in 2026. We have found that figure only in The Pointer’s report, not in a City document.

That matters for what there is to ask about. If a project is late because it is unfunded, the question is a budget question and a councillor can only lobby. If it is late because of how the work is sequenced and procured, the question is about process and timelines — which council does control, and which a candidate can be asked to commit to.

A different question is being asked inside the City, and it is a bigger one

Added 2026-09-05. Everything above treats Lisgar as a delivery problem: four stations were planned, two were running as of June 30, 2026, and the fourth is late. The City’s own Stormwater Advisory Committee has been asking something else — whether the assumptions the area was designed on still hold.

On 17 February 2026, citizen member Paul Bunyard, as the minutes record it, asked “if there has been an analysis on whether creek banks could overtop and flood homes along the main street in Lisgar, given upstream changes and shifts since the area’s original design.” He went on to ask who is responsible for monitoring those changes and protecting residents.

Part of the reply went outside the City. To the first question, a City manager replied that the conservation authorities are undertaking flood plain analysis, using advanced modelling, to update the flood lines, with City staff included on the committee doing the work; to the second, the same manager spoke to the City’s responsibility for managing stormwater and to the conservation authorities. The minutes do not say which flood lines are being updated or whether Lisgar’s are among them — but in that work Mississauga is a participant rather than the author.

Then the committee built itself a way to keep asking. On 17 February it voted to establish a subcommittee to make site visits to stormwater infrastructure and discuss technical matters related to flood control; members were appointed on 27 April and a third added on 8 June. By 8 June 2026 that subcommittee was discussing Lisgar directly. Reporting on those discussions, Bunyard spoke to “the need for a better understanding of conservation area limits, creek flow, flood lines, and the interface between subdivision design and larger storm events”, and suggested exploring whether upstream holding or retention in the broader area is possible.

And it asked for a third conservation authority. The committee directed staff to coordinate a subcommittee meeting with Conservation Halton to examine the Lisgar-area flooding issues. Conservation Halton’s watershed takes in about 4% of Mississauga, and Mississauga has two members on its board, appointed by the Region of Peel on 8 December 2022 (Resolution 2022-841): Councillor Sue McFadden, who represents Ward 10, and Councillor Alvin Tedjo. Mississauga councillors also sit on Credit Valley Conservation and the Toronto and Region Conservation Authority, all three now subject to direction by a provincial agency. Why Conservation Halton is the body being asked about Lisgar is not stated in the minutes. The pumping stations on this page sit along Sixteen Mile Creek, and Conservation Halton gave notice in October 2025 of a public engagement session for an East Sixteen Mile Creek Flood Hazard Mapping Study; whether that study covers Lisgar is not established here.

Corrected 2026-10-08. This passage said Mississauga appoints its councillors to Credit Valley and Toronto and Region “and not, so far as we have established, to Conservation Halton”. Mississauga has two members on Conservation Halton, and the Region of Peel makes the appointments to all three authorities.

The reason this belongs on a page about a late pumping station: the four stations are designed to pump water out of the foundation drain collector sewers when it reaches a pre-determined level, reducing basement water infiltration. The committee’s question is a different one: whether the creek itself could overtop and flood homes. So “when will it be finished” is only half the question. The other half is whether the flood protection planned for Lisgar still answers that risk, and who decides that — and on the record so far, the flood-line part of that work is being done by the conservation authorities, with City staff on the committee doing it.

Fact-check

confirmed This entry in the ledger →

Flooding in Lisgar dates to 2008; residents cite roughly $125 million in cumulative losses (a residents'-association figure, not an independently audited City figure). Two of four planned pumping stations were operational by 2025, a third south of Doug Leavens Boulevard expected fully operational in July 2026 (control panel tested, remaining equipment still under test as at June 30, 2026), and the fourth — at the east edge of Osprey Marsh south of Osprey Boulevard, detailed design COMPLETE and construction scheduled to begin later in summer 2026 per Coun. McFadden on June 30, 2026 — was, per INsauga on June 30, 2026 citing an earlier City statement, on track to open in 2027 despite resident requests to fast-track it to 2026. THE DELAY IS NOT A FUNDING ISSUE: at the September 2025 council meeting, City director Emma Calvert stated budgets had been allocated annually and that the projects proceed individually through design, tender and construction, which accounts for the schedule; $5.6 million was approved by council for the fourth station's design and construction, according to a City statement given to The Pointer on 2025-09-12 (PRESS-REPORTED — the statement is carried only by that outlet, and no City primary reached in the 2026-08-28 spot-check states it), with construction expected to start in 2026. Residents at that meeting also urged Mayor Parrish to use strong-mayor powers to accelerate it.

Developments

Dated, sourced updates on this issue, from the Journal.

2026-06-18 · confirmed

The City has published its 2026 Roads and Stormwater Capital Plan, and the Ward 10 sheet records where the Lisgar pumping stations stand in the City's own words rather than in an account of them. It lists three stormwater management projects for the ward this year. Pumping Station #3, at Doug Leavens Boulevard and Sixteen Mile Creek, appears as a new pumping station at the Construction phase. Pumping Station #4, at Osprey Boulevard and Sixteen Mile Creek, appears as a new pumping station at the Design/Construction phase. The third project is pond dredging and rehabilitation at SWMF 5601, Osprey Marsh, at Ninth Line and Parkgate Drive. The document also lists a downspout disconnection pilot in Block 7 of Lisgar — Black Walnut Trail and Cactus Gate, Apricot Street and Gumwood Road — at the Design phase, marked as not reflected on the capital plan mapping. Two of the three stormwater projects, station #3 and the Osprey Marsh dredging, carry an asterisk the document defines as indicating "that the project was carried over from the previous year"; station #4 does not. The stations after the first were set by a completed Schedule B Municipal Class Environmental Assessment, which the City published a Notice of Study Completion for, and which determined the number, preferred locations and types of future station from fourteen alternatives narrowed across three areas; the first, at the Cactus Gate Parkette, was begun in 2020 under the City's October 2017 Updated Action Plan. THIS ENTRY RECORDS WHAT THE CITY'S PLAN SAYS AND NOT WHAT HAS BEEN FINISHED. A project listed at the Construction phase and carried over from the previous year is consistent with work still under way, and the document does not state that any station is operational. The plan is dated June 2, 2026 and was published on June 18.

2026-06-08 · confirmed

Mississauga's Stormwater Advisory Committee has directed staff to coordinate a subcommittee meeting with Conservation Halton to examine flooding in the Lisgar area. The direction was given at the committee's meeting of June 8, 2026, after citizen member Paul Bunyard spoke to subcommittee discussions about Lisgar and, in his words as recorded in the minutes, the need for a better understanding of conservation area limits, creek flow, flood lines, and the interface between subdivision design and larger storm events. He also raised whether upstream holding or retention functions might be possible in the broader area. The subcommittee itself is new: the committee voted to establish it on February 17, 2026 to undertake site visits to city-wide stormwater infrastructure and discuss technical matters related to flood control, appointed two citizen members to it on April 27 and a third on June 8, each for a term ending in November 2026 or until a successor is appointed. WHAT MAKES THIS A DEVELOPMENT RATHER THAN A MEETING NOTE is which body was asked for. Mississauga councillors sit on Credit Valley Conservation and the Toronto and Region Conservation Authority, and two sit on Conservation Halton, all appointed by the Region of Peel. The minutes do not say why Conservation Halton is the body being asked about Lisgar and this entry does not speculate. Separately, at the committee's February 17 meeting a City manager told members that the conservation authorities are undertaking flood plain analysis using advanced modelling to update flood lines, with City staff included on the committee doing that work. Those are the same authorities that have been subject to direction by the Ontario Provincial Conservation Agency since November 2025. NOT ASSERTED HERE: that any flood line has changed, that Lisgar's mapping is out of date, or that the subcommittee meeting has taken place. What is recorded is that the City's own advisory committee asked who is responsible for monitoring change and protecting residents, and went looking outside the City for part of the answer. Corrected 2026-10-08: this entry said "this site has not established that Mississauga appoints anyone to" Conservation Halton, and listed "that Conservation Halton has jurisdiction in Mississauga" as not asserted. Conservation Halton's watershed takes in about 4% of the city, and the Region of Peel appointed two Mississauga councillors to its board on 8 December 2022.