The tension: Ward 3's Dundas corridor carries designated flood-hazard land, and the works meant to fix it are not scheduled for construction until 2027–2028 — while development on the corridor is being decided now. The two live applications sit differently: the City's own hazard mapping puts 1995 Dundas East partly inside hazard land, and 1225 Dundas East — recommended for approval by Planning and Development Committee on 2026-09-08 and approved by Council on 2026-09-16 — outside it, about 9 metres away. But the applicant's own floodplain report, filed in August 2024, says the site is within the current regulatory floodplain of Little Etobicoke Creek, and the committee recommended approving 16 storeys where the Official Plan permits 3 to 12.

Parts of Ward 3's Dundas Street East corridor are designated flood-hazard land, where Little Etobicoke Creek spills near the Dixie Road bridge in high flows. The City's fix is funded, but construction is scheduled for early 2027 to late 2028.

Development on the corridor is being decided before then. Council approved the 1225 Dundas East applications on 2026-09-16. The City's hazard mapping puts that parcel outside hazard land, about 9 metres away, but the applicant's own floodplain report says the site is within the creek's regulatory floodplain. A second application, 1995 Dundas East, is partly inside hazard land and under review.

So the buildings come first and the flood protection second. That may be manageable. What is open is who decides, on the record, what protects people in between, and whether what a flood report recommends becomes a binding condition of approval. The questions below ask both.

Resolution Options

Ways this tension could be resolved. Each question below tests one of them.

Questions you can ask

To: ward-3The Dixie-Dundas flood works are not scheduled for construction until 2027 to late 2028. Will you commit that no development in the area those works are meant to protect receives final approval before those works are built — or, if that isn't workable, that every approval publishes exactly what protection exists in the meantime?

Tests: Settle the interim protection before approving

Heard an answer to this?

To: ward-3One application on this corridor, 1225 Dundas East, has filed a floodplain mitigation report. Will you commit to the measures in any such report being written into the approval as binding, enforceable conditions rather than remaining recommendations in a consultant's study?

Tests: Make flood measures binding conditions

Heard an answer to this?

Candidates on record

No candidate is on record on this issue yet. Every candidate in this race is searched the same way. Only candidates who have said something in public on this issue are named here, with a link to the source; the others are counted by race below. The full record for every candidate is on Candidates.

Ward 3

5 candidates searched 2026-10-09: no public position found yet. Every candidate in this race →

The full story

The record behind the questions, with a source at each claim.

Parts of Ward 3’s Dundas Street East corridor are designated flood-hazard land — and which parts turns out to decide a great deal, so the word is load-bearing. Flooding here comes from Little Etobicoke Creek, which spills near the Dixie Road bridge in high flows.

The City is fixing it. The Dixie-Dundas Flood Mitigation project’s proposed solution, now in detailed design, includes widening and deepening the creek, replacing bridges, relocating utilities and improving trails. It is fully funded: $24.2 million federally through the Canada Housing Infrastructure Fund in 2025, $24.4 million provincially through the Municipal Housing Infrastructure Program, plus the City’s own budget.

The timing is the issue. Detailed design runs through fall 2026. Key utility relocations are already under way, with completion estimated for late 2026. Contractor pre-qualification runs into early 2027. Construction: early 2027 to late 2028.

The two applications sit differently, and it matters which

The corridor carries designated hazard land, but the two live applications are not both in it. We queried the City’s own Natural Hazards mapping through its open-data service, testing the parcels rather than the addresses:

Application Parcel intersects designated natural-hazard land?
1225 Dundas East (OZ/OPA 22-20 W3) — recommended for approval 2026-09-08, approved by Council 2026-09-16 No. The nearest hazard land is about 9 metres away (corrected 2026-10-02; previously “50 to 75 metres”)
1995 Dundas East (OZ/OPA 25-5 W3) — under review Yes, the parcel intersects hazard land

A control point placed inside a known hazard polygon returned a hit, so the “no” is a measurement rather than a failed query.

It may bear on something a reader would otherwise find strange. The staff report recommending 1225 Dundas East for approval never mentions flooding — no floodplain, no Special Policy Area, no conservation authority among the commenting agencies. The report gives no reason for that silence. The parcel lying outside the mapped hazard land does not settle it. The applicant’s Floodplain Mitigation Report — a memo from Stantec Consulting dated 7 August 2024, filed with the August 2024 resubmission — says “the Site is located within the current regulatory floodplain associated with Little Etobicoke Creek”, with Regional-storm flood depths on the City’s existing-conditions mapping ranging “from ~1m of flood depth at the northeast corner to ~0.10-0.30 m at the southwest corner”. It says the site is not in a Special Policy Area, and concludes the development “should not be restricted to proceed based on flood related concerns”, relying on proposed floor elevations it expects to be at or above the Regional flood level and on the City’s creek works.

Two limits on that check, because they bound what it proves. The layer is the 2010 Official Plan mapping and Mississauga Official Plan 2051 has been in effect since 2026-03-24, so a boundary could have moved since. And natural-hazard land is not the same instrument as a Special Policy Area; the City’s open-data catalogue carried no SPA layer when we searched its 328 datasets on 2026-10-02, so whether a Special Policy Area applies here is not tested by this check.

So the flood question on this corridor is live on both applications — on 1995 Dundas East through the City’s hazard mapping, and on 1225 Dundas East through the applicant’s own floodplain report.

The applications

Two carry Ward 3 file numbers:

A close version of our question was asked in the room, in April

Added 2026-09-05. A close version of the question this page puts to candidates — what protects people in the meantime — was put to City staff on 27 April 2026 by a citizen member of the City’s own Stormwater Advisory Committee, and the exchange is in the minutes.

Mike Gaudet, a citizen member, spoke to how residents south of Little Etobicoke Creek could face increased flood risk during the construction period, and inquired about interim flood protection measures. The recorded answer, from the Manager of Stormwater Assets & Programming, was that “appropriate construction phasing and safeguards would be considered.”

That is a real answer and it is not yet a commitment, which is exactly the gap a candidate can be asked to close. The construction period runs early 2027 to late 2028 — years, not weeks — and the risk being described is the risk of the fix, not of the problem.

The same committee is watching this project. Its 17 February 2026 meeting took an update on Dixie-Dundas and pressed on the level of flooding the works are designed to protect against, when residents can expect completion, and student safety at St. Edmund School given potential flooding through the school yard — which produced a formal letter to the Dufferin-Peel Catholic District School Board asking for the school’s evacuation plan. On 8 June the committee directed staff to bring a high-level update on the project and on how the City communicates stormwater resilience work publicly.

So the timing question below is not one nobody has raised. It has been raised inside the City’s own advisory structure, at more than one meeting, including by its citizen members — and it is still open.

So the sequence on the table is: decide the buildings first, build the flood protection second. That may well be manageable. One flood report is on file across the two applications — a Floodplain Mitigation Report filed for 1225 Dundas East in August 2024 — and the 1995 Dundas East file, the one whose parcel is in hazard land, lists none among its February 2025 documents. The open question is whether what such reports recommend becomes a binding condition of approval, and whether anyone has decided on the record what protection applies if an approval lands years before the creek is widened.

Updated 2026-09-13. On Tuesday, September 8, 2026, Planning and Development Committee recommended that Council approve the applications, as set out in the staff report of 19 August 2026. Its report to Council, Report 10-2026, records this as recommendation PDC-0044-2026: two 16-storey apartment buildings on a six-storey podium with 553 units and ground-floor commercial uses, plus 34 back-to-back townhouses, with staff to return to Council with the implementing documents and by-laws. One oral submission was received.

Two things in that wording matter to a resident. First, the committee’s decision is a recommendation. Council approved the applications on Wednesday, September 16, 2026, taking up Report 10-2026 as item 11.1 on its agenda. The City’s summary of that meeting, published September 23, 2026, says: “Plans have also been approved for 1225 Dundas Street East, including two 16-storey apartment buildings containing 553 units and 34 back-to-back townhomes.” It gives no vote, and none is stated here. The official plan amendment and zoning by-law that actually change what can be built came back to Council after that, and (updated 2026-10-13) Council passed both on Tuesday, September 29, 2026: Official Plan Amendment 18 (By-law 0163-2026), which changes the site’s designation from Mixed Use to Residential High-Rise and permits a maximum height of 16 storeys, and Zoning By-law 0164-2026. The City’s notice of passing, dated October 8, 2026, gives 4:30 p.m. on October 28, 2026 as the last day to appeal to the Ontario Land Tribunal; if no appeal is received by then, the City’s decision is final. The zoning by-law does not come into force until the amendment does. Only the applicant, the Minister, or an owner of affected land, a specified person or a public body who made written or oral submissions to Council before its decision may appeal. Second, the rezoning approval would have been void “unless a zoning by-law is passed within 18 months of the Council decision”; the September 29 by-law meets that condition.

The committee acted on the notice’s description of the building — two 16-storey towers — not the superseded 18-storey scheme still summarised on the City’s application page. Report 10-2026 does not record how members voted. The committee’s minutes of 2026-09-08, read 2026-10-02, do: the recommendation was moved by Councillor C. Fonseca and carried 11 to 0.

⚠️ The meeting date moved once. An earlier version of this page gave Monday, August 24 — that meeting did not happen.

The City rescheduled it on August 13, and its revised notice said so at the top of its first page: PUBLIC MEETING RESCHEDULED. REVISED DATE: TUESDAY, SEPTEMBER 8, 2026 (Previously Monday, August 24, 2026). If you had set aside August 24 to attend or speak, we are sorry for the wasted trip.

Added 2026-09-05. The report was obtained by a person opening it in a browser, because the City’s agenda system refused every automated request we made that day.

The report is dated 19 August 2026, from Andrew Whittemore, Commissioner of Planning and Building, prepared by Jaspreet Sidhu, Development Planner. It recommends that the applications be approved, and that staff return to Council with the implementing by-laws.

The proposal is 587 units — 553 apartments in the two towers, plus 34 townhouses — and all of it is purpose-built rental. (This site published “1,043 units” for weeks with no source behind it; that figure was removed on 2026-09-05 and this is the figure in the City’s own report.) The report is not fully consistent with itself: its unit-mix table totals 518 apartments, and one passage counts 35 townhouses; 553 and 34 are the figures in its recommendation, and 587 its stated total.

And this is the finding. Schedule 8 of Mississauga Official Plan 2051 sets a permitted height range of 3 to 12 storeys for this site. The proposal is 16, and the report says so plainly:

While the proposed development exceeds the height currently contemplated for the subject lands, staff are satisfied that the proposed height is appropriate, having regard for the site’s location within the MTSA, its frontage on Dundas Street, and the planned evolution of the Dundas Street Corridor.

The height set for this site has changed with each planning instrument since 2012, and the committee has now recommended more than any of them:

When Instrument Maximum height
2012-11-14 Mississauga Official Plan 4 storeys
2022-08-10 OPAs 141–144, corridor and transit-station policies — adopted by Council, then appealed to the Ontario Land Tribunal 9 storeys
2024-05-09 OPA 144 in effect 3 to 9 storeys
2026-03-24 Mississauga Official Plan 2051 3 to 12 storeys
2026-09-08 recommended for approval by Planning and Development Committee 16 storeys
2026-09-16 applications approved by Council 16 storeys
2026-09-29 Official Plan Amendment 18 (By-law 0163-2026) and Zoning By-law 0164-2026 passed by Council; last day to appeal 2026-10-28 16 storeys

That is the mechanism question this ward actually raises: not whether 16 storeys is too tall — that is a matter of opinion — but what a published height range is for, if a recommendation can exceed it and recommend approval on the same page that records the excess.

And there is a second set of heights that does not reach this application either. Added 2026-09-05. The staff report places the site “within the Dixie Major Transit Station Area (MTSA)”, and weighs its shadow impacts against “the City’s intensification objectives within a Protected Major Transit Station Area”. In July 2026 Council passed By-law 0132-2026, which sets minimum and maximum heights and densities on certain lands in the city’s protected major transit station areas, including lands along the Dundas bus rapid transit corridor. That by-law is the subject of the Clarkson issue, because in a protected station area the Planning Act removes the appeal of height and density policies.

The staff report never mentions By-law 0132-2026 once. It amends By-law 0225-2007 — the 2007 zoning by-law — and proposes an exception zone under it. That is dated 19 August 2026, three weeks after 0132-2026 was passed.

The by-law’s transition clause does not explain it. The clause sits inside the by-law’s hatched “PMTSA Special Area”, and it covers a complete site plan or draft plan of subdivision application, or a building permit application, received before 29 July 2026, which may be approved if it complies with By-law 0225-2007 “as it read immediately before” that date. This is an official plan amendment and rezoning application, which is none of those. What we can say is narrower: a rezoning is itself an amendment to By-law 0225-2007 — By-law 0132-2026 amends the same by-law — and this one creates its own exception zone for the site. Whether 0132-2026 changed this site’s zoning at all we could not tell: the staff report still describes the property as “currently zoned C3 (General Commercial)”, and the by-law’s schedules are maps we could not resolve to a single parcel. (Corrected 2026-10-02. This paragraph previously said the clause “continues applications filed before 29 July 2026 under the 2007 by-law”.)

The practical effect is the point worth carrying to a candidate: the heights Council set for transit station areas in July 2026 do not govern this application, which the committee has recommended at 16 storeys against an Official Plan range of 3 to 12. A resident who read that Council had set new standards around transit stations would reasonably assume otherwise.

Two other things in the report are not the City’s decision at all. Affordable units are not required through inclusionary zoning, because “Inclusionary Zoning requirements are currently paused in the City of Mississauga in accordance with Provincial regulation.” And there are no minimum parking requirements, because provincial rules remove them inside a major transit station area. Both are provincial constraints on a municipal decision, which is what this site exists to make visible.

The recorded public engagement was small. A community meeting held by the ward councillor in July 2022 drew “approximately five people attending virtually”, and at the statutory public meeting in January 2023 “Two people were in attendance and provided comments.” The same report also records that at that January 30, 2023 meeting “Four oral submissions were also received.”

What we could not reach, and why it is stated rather than hidden

Checked 2026-09-05. The staff report is not published on the City’s application page — its five document groups run to the public notices and four submission sets, and carry no corporate report of any kind. The report lives on the committee agenda instead.

And on 2026-09-05 we could not read the agenda system at all. escribemeetings.com returned HTTP 403 to three separate tools across three layers — the portal root, a meeting page, and a document URL this project had previously downloaded successfully. That is a change from its recorded state and is logged as one.

So the report above was read by a person, not by us. A human opened the agenda in a browser and copied the text back; it is archived in full, with a note recording how it was obtained. We mention it because this site’s claim is traceability, and “how did you get this” is part of that: the document is a City public record either way, but the route to it that day was manual.

The file has been resubmitted three times, and the City’s own page describes the wrong building

Added 2026-09-05. The application page carries five document groups: the public notices, the original July 2022 submission (22 files), and three resubmissions — August 2024 (57 files), July 2025 (81 files) and May 2026 (53 files).

And the staff report accounts for the height. During review “the building heights were reduced from the interim proposal of 18 storeys to 16 storeys.” So the application page’s 18-storey summary describes a superseded scheme, and the statutory notice describes the current one. The report gives a figure only for the height change — it says density and commercial space also changed between submissions, but does not mention the summary’s 612 units, 626 m² of retail or 30 townhouses — so which earlier submission that summary line was written from is not established. The City’s own report records the change; the City’s own web page was never updated to match it, and still had not been on 2026-09-05.

(We inferred this before we could read the report — the July 2025 drawing set includes a sheet titled “Floors 14-18” while the May 2026 set runs Floor 1 to Floor 16 and stops. The report then confirmed it. Keeping the inference on the record because it was right, and because it shows what a file list can tell you when the document itself is out of reach.)

The notice and the application page describe different buildings

Both documents are the City’s, and they do not match.

What it says is proposed
The statutory notice (July 30, and a second copy on the application page) Two 16-storey apartment buildings on a six-storey podium with ground-floor commercial, plus 34 four-storey back-to-back townhouses
The application page’s summary line (marked Updated: August 13, 2026 — re-read that day) One 18-storey mixed-use building, 612 apartments, 626 m² of retail, 30 townhouses

The contradiction survived an update. We first recorded this on August 11, when the page was marked Updated: August 10. The City revised the page on August 13 to carry the rescheduled meeting date — and left the building description untouched. Re-read 2026-08-24: it still says one 18-storey building with 612 apartments. So this is not a page nobody has looked at; it is a page that was edited, that day, without the summary being corrected.

We had published the second version. Two statutory notices carry the first and agree with each other, so this page now leads with that — the notice is the document that tells residents what they are coming to speak about.

The committee’s recommendation settles which one it acted on: PDC-0044-2026 describes the notice’s two 16-storey buildings, not the application page’s single 18-storey one.

This is not an accusation of concealment — a summary line nobody updated is much more likely than a decision. But a resident relying on the City’s own application page was reading about a building that was no longer proposed.

Correction, 2026-07-30. This entry previously described “three towers of 29–41 storeys” and roughly 3,027 units near “Applewood Creek hazard lands”, citing City file OZ/OPA 22-32 W1. Those facts belong to Ward 1, not Ward 3: OZ/OPA 22-32 W1 is 1250 South Service Road, the Dixie Outlet Mall lands (four buildings, 4–19 storeys, 997 units), and the 3,027-unit figure belongs to 1580–1650 Dundas Street East (OZ/OPA 22-22 W1). The entry has been rebuilt on the City’s own Ward 3 application records.

Fact-check

confirmed This entry in the ledger →

Corrected 2026-09-05. It said development applications are 'being decided now in a designated flood-vulnerable area'. For the application actually being decided, the City's 2010 natural-hazard mapping does not show it, but the applicant's own Floodplain Mitigation Report (Stantec, 7 August 2024) says 'the Site is located within the current regulatory floodplain associated with Little Etobicoke Creek' (corrected 2026-10-02). Queried the City's own 'Mississauga Official Plan (2010) Natural Hazards' layer through its ArcGIS open-data service, testing PARCELS rather than address points: the 1225 Dundas East parcel intersects NO natural-hazard polygon and the nearest hazard land is about 9 metres away (corrected 2026-10-02; previously '50 to 75 metres'), while the 1995 Dundas East parcel DOES intersect one. A control point inside a known hazard polygon returned a hit, so the negative is a measurement and not a failed query. TWO LIMITS ON THAT CHECK, STATED: the layer is the 2010 Official Plan mapping and MOP 2051 has been in effect since 2026-03-24; and natural-hazard land is not the same instrument as a Special Policy Area, for which the City's open-data catalogue carried no layer when its 328 datasets were searched on 2026-10-02. THE CONSEQUENCE MATTERS MORE THAN THE CORRECTION: the staff report recommending approval never mentions flooding, floodplain, Special Policy Area or any conservation authority, and we went looking for that silence expecting it to mean something. The report gives no reason for that silence; the applicant's own Floodplain Mitigation Report, filed with the August 2024 resubmission, places the site within the current regulatory floodplain of Little Etobicoke Creek. Publishing the silence as a finding would have been a false accusation against a named City department three days before a decision. THE CORRIDOR-LEVEL CLAIM SURVIVES — 1995 Dundas East is in hazard land and the flood works are real, funded and unbuilt until 2027-2028 — and the applicant's own report places 1225 Dundas East within the regulatory floodplain as well. ALSO CORRECTED 2026-09-05: this entry said 1225 Dundas East 'has filed a Floodplain Mitigation Report, and a further Flood Mitigation Report on resubmission', implying two flood documents. THERE IS ONE — 'Floodplain Mitigation Report – August 2024' — and it is the only flood or floodplain report in any of the file's five document groups. NEITHER the July 2025 resubmission (81 files) NOR the May 2026 resubmission (53 files) contains a flood report of any kind, so the design Planning and Development Committee recommended for approval on 2026-09-08 is TWO RESUBMISSIONS NEWER THAN THE FLOOD ANALYSIS a resident can read. ALSO ADDED: the file has been resubmitted THREE times (August 2024, July 2025, May 2026), which this entry did not know; and the May 2026 drawing set runs Floor 1 to Floor 16 and stops, where July 2025 included a sheet titled 'Floors 14-18' — evidence that the application page's 18-storey summary line describes a SUPERSEDED scheme, inferred from file names rather than from the drawings themselves. The staff report, dated 2026-08-19 from the Commissioner of Planning and Building, is absent from the application page and was read from the committee agenda by a person in a browser on 2026-09-05. It recommends approval at 16 storeys where Mississauga Official Plan 2051 Schedule 8 permits 3 to 12. The City's Dixie-Dundas Flood Mitigation project page says the Dixie-Dundas community is subject to flooding. Flooding originates from Little Etobicoke Creek, which spills near the Dixie Road bridge in high flow conditions. The proposed solution for the City's Dixie-Dundas Flood Mitigation project, now in detailed design, includes widening and deepening the creek, bridge replacements, utility relocations and trail improvements. It is fully funded — $24.2M federal (Canada Housing Infrastructure Fund, 2025) and $24.4M provincial (Municipal Housing Infrastructure Program, Health and Safety Water Stream) plus City budget — but detailed design runs through fall 2026, key utility relocations are under way with completion estimated for late 2026, and CONSTRUCTION IS SCHEDULED FOR EARLY 2027 TO LATE 2028. Two active applications carry Ward 3 file numbers: 1225 Dundas St E (OZ/OPA 22-20 W3) — TWO 16-STOREY apartment buildings on a six-storey podium with ground-floor commercial, plus 34 four-storey back-to-back townhouses, per the statutory public meeting notice of 2026-07-30. THE CITY DISAGREES WITH ITSELF HERE AND BOTH SURFACES ARE ITS OWN: the application page, marked "Updated: August 13, 2026", still summarises a superseded scheme as one 18-storey mixed-use building with 612 apartments, 626 sq m of retail and 30 townhouses. Two separate statutory notices carry the revised description and agree with each other; this entry follows them, because the notice is the document that tells residents what they are coming to speak about. The staff report records that the buildings were reduced from an interim 18 storeys to 16 during review, and on 2026-09-08 the committee recommended the notice's version. One Floodplain Mitigation Report (Aug 2024) is on file; and 1995 Dundas St E (OZ/OPA 25-5 W3 and 21T-M 25-1 W3) — two towers of 24 and 25 storeys plus 15 townhouses, submitted February 2025, under review. PUBLIC MEETING RESCHEDULED — CORRECTED 2026-08-24. The date established 2026-08-11 was Monday, August 24, 2026 at 1:30 p.m. THE CITY RESCHEDULED IT ON 2026-08-13 TO TUESDAY, SEPTEMBER 8, 2026 at 1:30 p.m., same Council Chamber, and this site published the superseded date for eleven days. The revised notice states it in terms: 'PUBLIC MEETING RESCHEDULED. REVISED DATE: TUESDAY, SEPTEMBER 8, 2026 (Previously Monday, August 24, 2026)', Revised Date of Notice August 13, 2026. ON 2026-09-08 PLANNING AND DEVELOPMENT COMMITTEE RECOMMENDED APPROVAL — recommendation PDC-0044-2026 in Report 10-2026: two 16-storey apartment buildings on a six-storey podium with 553 units and ground-floor commercial uses, plus 34 back-to-back townhouses, as set out in the staff report of 2026-08-19, with staff to return to Council with the implementing documents and by-laws. One oral submission was received. The report records no vote count; the committee's minutes of 2026-09-08, read 2026-10-02, record the recommendation as moved by Councillor C. Fonseca and carried 11 to 0. Council approved the applications on 2026-09-16, taking up Report 10-2026 as agenda item 11.1: the City's council recap published 2026-09-23 says 'Plans have also been approved for 1225 Dundas Street East, including two 16-storey apartment buildings containing 553 units and 34 back-to-back townhomes', and gives no vote. On 2026-09-29 Council passed the implementing by-laws: Official Plan Amendment 18 (By-law 0163-2026), changing the designation from Mixed Use to Residential High-Rise with a maximum height of 16 storeys, and Zoning By-law 0164-2026, per the City's Notice of Passing dated 2026-10-08 (updated 2026-10-13). The last day to appeal to the Ontario Land Tribunal is 2026-10-28, 4:30 p.m.; if no appeal is received the City's decision is final. The committee's rezoning approval would have been void unless a zoning by-law was passed within 18 months of the Council decision; the 2026-09-29 by-law meets that condition.

Developments

Dated, sourced updates on this issue, from the Journal.

2026-09-29 · confirmed

Council passed Official Plan Amendment 18 (By-law 0163-2026) and Zoning By-law 0164-2026 for 1225 Dundas Street East on September 29, 2026. The site changes from Mixed Use to Residential High-Rise with a maximum height of 16 storeys, where Mississauga Official Plan 2051 had set 3 to 12, and the zoning permits two 16-storey apartment buildings on a six-storey podium with ground-floor commercial uses and 34 four-storey back-to-back townhouses. The last day to appeal to the Ontario Land Tribunal is October 28, 2026; if no appeal is received by then, the City's decision is final.

2026-09-08 · confirmed

Planning and Development Committee recommended on September 8, 2026 that Council approve 1225 Dundas Street East: two 16 storey apartment buildings on a six storey podium with 553 units and ground-floor commercial uses, plus 34 back-to-back townhouses, as set out in the staff report of August 19, 2026. The Official Plan range for the site is 3 to 12 storeys. The recommendation, PDC-0044-2026, is in the committee's Report 10-2026. Updated 2026-10-13: Council approved the applications on September 16, 2026 and passed the implementing by-laws on September 29, 2026 (see that day's entry). One person made an oral submission. The committee acted on the two-16-storey description in the statutory notice, not the 18-storey scheme the City's application page still summarises. The report records no vote count; the committee's minutes, read 2026-10-02, record the recommendation as moved by Councillor C. Fonseca and carried 11 to 0. This site is outside the natural-hazard land on the City's 2010 Official Plan mapping, but the applicant's own floodplain report, filed in August 2024, places it within the current regulatory floodplain of Little Etobicoke Creek.

2026-09-05 · confirmed

City planning staff have recommended APPROVAL of 1225 Dundas Street East, and the recommendation went to the Planning and Development Committee on September 8, 2026. The staff report, dated August 19, 2026 from the Commissioner of Planning and Building, recommends approving official plan and rezoning applications for two 16 storey apartment buildings on a six storey podium containing 553 dwelling units, plus 34 four storey back to back townhouses — 587 units in total, all purpose-built rental. THE HEIGHT EXCEEDS WHAT THE OFFICIAL PLAN PERMITS, AND THE REPORT SAYS SO: Schedule 8 of Mississauga Official Plan 2051 sets a permitted range of 3 to 12 storeys for this site, and the report states that "while the proposed development exceeds the height currently contemplated for the subject lands, staff are satisfied that the proposed height is appropriate", citing the site's position in the Dixie Major Transit Station Area and on the Dundas Street corridor. The height set for this site has changed with each planning instrument since 2012 — a maximum of 4 storeys under the 2012 official plan, 9 storeys under the 2022 corridor and transit-station amendments (adopted by Council, then appealed), a range of 3 to 9 when Official Plan Amendment 144 took effect on May 9, 2024, and 3 to 12 when Mississauga Official Plan 2051 came into effect on March 24, 2026. The proposal is 16. The report also records that the applicant reduced the buildings from an interim 18 storeys to 16 during review, which explains a contradiction this site published on August 11: the City's own application page still summarises the project as one 18 storey building with 612 apartments, a superseded scheme. Two other mechanisms appear in the report and neither is the City's choice: inclusionary zoning is "currently paused in the City of Mississauga in accordance with Provincial regulation", so no affordable units are required through inclusionary zoning; and there are no minimum parking requirements in a major transit station area. Recorded public engagement was a councillor's community meeting in July 2022 attended by about five people and a statutory public meeting in January 2023 attended by two (the same report also records four oral submissions at that meeting). The City's own natural-hazard mapping, from its 2010 Official Plan, puts no hazard land on this parcel, with the nearest about 9 metres away. The applicant's own Floodplain Mitigation Report, filed with its August 2024 resubmission, says "the Site is located within the current regulatory floodplain associated with Little Etobicoke Creek". The staff report does not discuss flooding and gives no reason. See the correction on the issue page.

2026-07-30 · confirmed

The statutory notice for 1225 Dundas Street East is public, and it settles a date this site has been unable to give readers: the public meeting is MONDAY, AUGUST 24, 2026 at 1:30 p.m. in the Council Chamber, and Planning and Development Committee will receive a staff report and MAKE A DECISION about the project at it. The notice says advance registration by 12:00 p.m. on the Friday before is required to speak; its section on speaking in person says only that it is preferred. The staff report is due online one week ahead. THE NOTICE ALSO DESCRIBES A DIFFERENT BUILDING FROM THE ONE THE CITY'S OWN APPLICATION PAGE SUMMARISES, and both are the City's. The statutory notice — the document that tells residents what they are coming to speak about — says the applicant proposes TWO 16-STOREY apartment buildings on a six-storey podium with ground-floor commercial, plus 34 four-storey back-to-back townhouses. The application page, updated August 10, 2026, still summarises an earlier version of the proposal: one 18-storey mixed-use building, 612 apartments, 626 square metres of retail and 30 townhouses. We had published the application page's version. Two separate statutory notices carry the revised description and agree with each other, so this page now leads with that and says where the other figure comes from. Which is operative is a question for the City, not for us. The site could not previously give the meeting date because the application page's link to the notice pointed at teamsites.mississauga.ca, an internal host that does not answer publicly; that link now resolves to the public server, and the notice was in any case published on the City's public-notices feed on July 30.